Fullerton College Physical Education Complex
Construction currently is underway on the Fullerton College Physical Education Complex renovation project, one of the final projects in the Measure X Facilities Bond Program approved by voters in 2002.
The Physical Education Complex project includes a pool, field renovation, and physical education building remodel.
Schedule
| Phase 1 |
|
| Original Schedule |
|
| Pool - 3 Months |
|
| Start Date |
December 21, 2007 |
| Substantial Completion |
August 22, 2008 |
| Current Schedule |
|
| Pool - 16 months |
|
| Start Date |
December 27, 2007 |
| Substantial Completion |
April 30, 2009 |
| |
|
| Phase 2 |
|
| Original Schedule |
|
| PE/Field House - 13 Months |
|
| Start Date |
January 25, 2008 |
| Substantial Completion |
March 9, 2009 |
| Current Schedule |
|
| PE/Field House - 21 Months |
|
| Start Date |
September 2, 2008 |
| Substantial Completion |
May 18, 2010 |
Public Comment Form
Fullerton College Physical Education Complex Renovation Project Public Comment Form, April 2009
Neighbors Letter
Re: Community Notice of New Initial Study to Address Impact of Fullerton College Physical Education Complex Renovation Project, April 8, 2009
Meeting Summary
Fullerton College Neighbors Meeting Summary, March 11, 2009
Update Presentation to Board
Update Presentation to Board of Trustees, January 27, 2009
Background Board of Trustee Agenda Items
- City Zoning Exemptions for Cypress and Fullerton Colleges, December 9, 2003
- Environmental Impact Report (EIR) & Master Plan Projects, March 9, 2004
- Fullerton College Physical Education Contracts, May 27, 2008
- California Environmental Quality Act Compliance for Changes in the Sports Field, March 24, 2009
- Fullerton College Traffic Impact Study and Parking Study, April 14, 2009
- Fullerton College Physical Education Architectural Contract Amendment, April 14, 2009
Minutes from Board of Trustees Meetings:
http://www.nocccd.edu/Trustees/MtgMinutesArchive2008.htm
Facilities Bond Program 2008 Report to the Community:
http://www.nocccd.edu/Departments/FandF/FacilitiesBond/ReportToTheCommunity.htm
Also Available:
Copies of the following reports also may be viewed in the NOCCCD Offices by appointment at 714-808-4831 or publicaffairs@nocccd.edu:
- Draft Program Environmental Impact Report for the Fullerton College Master Plan,
November 2003
- Revised Final Program Environmental Impact Report for the Fullerton College Master Plan,
January 30, 2004
- Fullerton College/North Orange County Community College District Master Plan 1999